THE INFLUENCE OF POLICY ON SMELTER DEVELOPMENT PROJECTS ON IMPROVING PROJECT TIME PERFORMANCE

Authors

  • Salma Fadhilah Civil Engineering Study Program, Faculty of Engineering, University of Indonesia
  • Rossy Armyn Machfudiyanto Civil Engineering Study Program, Faculty of Engineering, University of Indonesia

DOI:

https://doi.org/10.35814/wy6am293

Keywords:

smelter, policy, project time performance, SEM-PLS

Abstract

To facilitate downstreaming in mining industry, the law requires holders of Mining Business Permits (IUP) and Work Contracts (KK) to establish smelters, namely mining processing facilities that function to increase metal content to a level that meets standards as raw materials for final products. From the policy factors found that policy has a role in the problem of delays in smelter construction in Indonesia. Therefore, evaluation and improvement of regulations as a solution to the problem need to be carried out so that smelter construction as an effort to implement mining downstreaming can be implemented properly. The study was conducted by collecting qualitative primary data which was analyzed using Structural Equation Modeling (SEM). In the relationship between policy variables and project time performance variables, Variable X3 Supervision and Variable X6 Force Majeure has a significant effect on the project time performance variable, while other variables do not have a significant effect.

References

Book

Catapotis, M., & Bassiakos, Y. (2007). Metallurgy in the Early Bronze Age Aegean. Oxford: Oxbow.
Hair, J. F., Hult, G. T., Ringle, C. M., & Sarstedt, M. (2013). A Primer on Partial Least Squares Structural Equation Modeling (PLS-SEM). Sage Publications.
Sholeh, M. N., & Fauziyah, S. (2023). Pengadaan Material Proyek Engineering Procurement Construction. Yogyakarta: Penerbit Pustaka Pranala.
Sugiyono. (2013). Metode Penelitian Kuantitatif, Kualitatif dan R & D. Bandung: ALFABETA.
Scientific Journal

Ali, Smith, Pitt and Choon. (2012). Contractors’ Perception of Factors Contributing to Project Delay: Case Studies of Commercial Projects in Klang Valley, Malaysia.
Ahda, N. (2021). Di Balik Larangan Ekspor Bijih Nikel Indonesia. Buletin APBN Vol. VI. Ed. 2, Februari 2021, 8-11.
Alfadil, M. O., Kassem, M. A., Ali, K. N., & Alaghbari, W. (2022). Construction Industry from Perspective of Force Majeure and Environmental Risk Compared to the COVID-19 Outbreak: A Systematic Literature Review. MDPI Sustainability 2022, 14, 1135, 1-22.
Contesa, M., Sintaningrum, & Rahmatunnisa, M (2018). Smelter : Inkonsistensi Kebijakan , Kendala dan Dampak di Indonesia. Responsive, Volume 1 No. 1 Oktober 2018 : 6-11.
Hassan, H., Mangare, J. B., & Pratasis, P. A. (2016). Faktor–Faktor Penyebab Keterlambatan Pada Proyek Konstruksi Dan Alternatif Penyelesaiannya (Studi Kasus : Di Manado Town Square III). Jurnal Sipil Statik Vol.4 No.11 November 2016, 657-664.
Ika, S. (2017). Kebijakan Hilirisasi Mineral: Reformasi Kebijakan untuk Meningkatkan Penerimaan Negara. Kajian Ekonomi Keuangan Vol. 1 No. 1 (2017), 43-67.
Khaidir, I. (2018). Faktor Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi Di Sumatera Barat. Jurnal REKAYASA (2018) Vol. 8, No. 01, 032‐049.
King, S. S., Rahman, R. A., Fauzi, M. A., & Haron, A. T. (2022). Critical analysis of pandemic impact on AEC organizations: the COVID-19 case. Journal of Engineering, Design and Technology Vol. 20 No. 1, 358-383.
Maulana, R., & Jamhir. (2018). Konsep Hukum Perizinan dan Pembangunan. Jurnal Justisia : Jurnal Ilmu Hukum, Perundang-undangan dan Pranata Sosial Vol 3, No 1, 90-115.
Meng, X., & Gallagher, B. (2012). The Impact Of Incentive Mechanisms On Project Performance. International Journal of Project Management, 352 – 362.
Nabut, Y. V., Henong, S. B., & Pattiraja, A. H. (2021). Analisa Faktor-Faktor Yang Paling Dominan Penyebab Keterlambatan Proyek . Jurnal Teknik Sipil Cendekia Vol 2 No 2, 1-9.
Natalia, M., Riswandi, Mirani, Z., Partawijaya, Y., & Misriani, M. (2018). Faktor Penyebab Kegagalan Akibat Keterlambatan Proyek Konstruksi Pada Bangunan Gedung di Kota Padang. Jurnal Ilmiah Rekayasa Sipil (JIRS) Vol. XV No. 2 Edisi Oktober 2018.
Remi, F. F. (2017). Kajian Faktor Penyebab Cost Overrun Pada Proyek Konstruksi Gedung. Jurnal Teknik Mesin (JTM): Vol. 06, Edisi Spesial 2017, 94-101.
Ruben, G., Sondakh, J., & Soeikromo, D. (2021). Kajian Yuridis Kewajiban Perusahaan Pertambangan Mineral Logam Dalam Membangun Fasilitas Pengolahan Dan Pemurnian (Smelter) Di Indonesia. Lex Administratum, Vol. IX/No. 1/Jan-Mar/2021, 1-10.
Sari, L. P., & Ariawan. (2023). Review Of Principles Of Quantitative Restrictions On Dispute Settlement“EU And US Lawsuit For The Indonesian Government's Nickel Export Ban Policy By The WTO Disputesettlement Body. International Journal of Educational Review, LawAnd Social Sciences (IJERLAS) Volumes 3 No. 5, 1376 - 1385.
Sarli, A., & Adianto, Y. L. (2017). Hambatan Penerapan Insentif Dalam Kontrak Kerja Konstruksi Pemerintah Dari Persepsi Pengguna Jasa. Jurnal Infrastruktur Vol. 3 No. 02 Desember 2017, 26-31.
Sihotang, E., & Suandika, I. N. (2023). Kebijakan Larangan Eksport Bijih Nikel Yang Berakibat Gugatan Uni Eropa Di Wort Trade Organization. Jurnal Raad Kertha Vol. 6, No. 1, 61-70.
Sugianto, F., & Rahayu, S. W. (2020). Implikasi Kebijakan dan Diskriminasi Pelarangan Ekspor dan Impor Minyak Kelapa Sawit dan Bijih Nikel Terhadap Perekonomian Indonesia. Jurnal Ilmu Hukum Volume 16 Nomor 2, 224-236.
Sugiarto, A. (2017). Implementasi Pengendalian Pemanfaatan Ruang dan Sanksi Administratif dalam Rencana Tata Ruang Wilayah Kabupaten Sidoarjo. Jurnal Kebijakan dan Manajemen Publik (JKMP), 5 (1), 41-60.
Tapada, R. F., Tampanguma, M. Y., & Mawuntu, J. R. (2022). "Akibat Hukum Penerapan Undang-Undang. Lex Privatum, Vol. 10 No. 4.

Regulations/Laws

Law Number 11 of 1967 concerning Basic Provisions on Mining
Law Number 4 of 2009 concerning Mineral and Coal Mining
Regulation of the Minister of Energy and Mineral Resources Number 25 of 2018 concerning Mineral and Coal Mining Business

Downloads

Published

2025-05-23

How to Cite

THE INFLUENCE OF POLICY ON SMELTER DEVELOPMENT PROJECTS ON IMPROVING PROJECT TIME PERFORMANCE. (2025). Jurnal Infrastruktur , 11(1), 45-52. https://doi.org/10.35814/wy6am293