WEATHER RISK MANAGEMENT IN BUILDING CONSTRUCTION PROJECTS BASED ON DATA ANALYSIS IN SOUTH KALIMANTAN
DOI:
https://doi.org/10.35814/99t3ct66Keywords:
Construction risk, Risk management, Weather mitigation, Severity Index, Probability Impact MatrixAbstract
The rainy season in South Kalimantan is characterized by high intensity and unpredictable patterns, posing significant risks to the success of building construction projects. These risks include material damage, reduced labor productivity, schedule delays, and increased project costs. This study aims to identify, analyze, and formulate mitigation strategies for risks caused by rainfall in construction projects within the region. Primary data were collected through questionnaires distributed to 30 respondents consisting of contractors, construction managers, and supervisory consultants, while secondary data were obtained from literature and project documents. The analysis involved validity and reliability testing of the instruments using SPSS, followed by the Severity Index method to measure the probability and impact of risks, and the Probability Impact Matrix to determine dominant risk levels. The results indicate that 25 risks factors were valid and reliable, with Cronbach’s Alpha values exceeding 0.9. The analysis identified seven high-risk variables, namely delays in material delivery, material damage due to humidity, decreased labor productivity, postponement of concrete casting, rescheduling of project activities, delays in managerial decision-making, and unexpected additional costs. Proposed mitigation strategies include contingency planning for logistics, material protection measures, flexible work scheduling, the application of adaptive construction technologies, and strengthened managerial coordination. These findings are expected to contribute to enhancing the resilience of construction projects against extreme weather conditions and serve as a foundation for developing adaptive risk management practices in Indonesia’s construction sector.
References
Ade, R. (2023). Analisis Risiko Pengaruh Musim Penghujan Terhadap Penyelesaian Proyek Konstruksi (Studi Kasus Proyek Bangunan Gedung Di Yogayakarta).
Afiq, M. (2021). Manajemen Risiko Pada Proyek Pembangunan Gedung Asrama Mahasiswa Uin Walisongo Tahun 2021. Akselerasi : Jurnal Ilmiah Teknik Sipil, 3(1), 70–80. Https://Doi.Org/10.37058/Aks.V3i1.3561
Ahmed, S., & El-Sayegh, S. (2024). Relevant Criteria For Selecting Project Delivery Methods In Sustainable Construction. International Journal Of Construction Management, 24(5), 512–520.
Akwaisua, A. M., Ekong, A., & Ansa, G. (2025). Enhancing Hazard Detection And Risk Severity Assessment In Construction Through Multinomial Naive Bayes And Regression. Journal Of Information Systems And Informatics, 7, 97–121.
Allan, R. P., Arias, P. A., Berger, S., Canadell, J. G., Cassou, C., Chen, D., Cherchi, A., Connors, S. L., Coppola, E., & Cruz, F. A. (2023). Intergovernmental Panel On Climate Change (Ipcc). Summary For Policymakers. In Climate Change 2021: The Physical Science Basis. Contribution Of Working Group I To The Sixth Assessment Report Of The Intergovernmental Panel On Climate Change (Hal. 3–32). Cambridge University Press.
Andrew, J., Cantik, B. K. P., Makmur, A., & Dharsono, M. S. (2025). Analisis Risiko Hujan Terhadap Penyelesaian Pekerjaan Struktur Pada Proyek Konstruksi. Jurnal Ilmiah Mahasiswa Teknik Dan Desain, 1(1), 169–175.
Berkelanjutan, J. T., Widiastuti, E., Karim, A., Yuliana, C., Nashrullah, E., & Widayanti, N. (2023). Optimalisasi Jumlah Unit Rumah Tiap Tipe Sesuai Kemampuan Daya Beli Masyarakat (Studi Kasus: Perumahan Di Kabupaten Banjar). Sustainable Technology Journal, 12(01), 27–34. Http://Jtb.Ulm.Ac.Id/Index.Php/Jtb
Dong, R. R., Muhammad, A., & Nauman, U. (2025). The Influence Of Weather Conditions On Time, Cost, And Quality In Successful Construction Project Delivery. Buildings, 15(3). Https://Doi.Org/10.3390/Buildings15030474
Ervianto, W. I. (2005). Manajemen Proyek Konstruksi Edisi Revisi. Yogyakarta: Andi.
Ghaeb, Hiba O., A. M. R. M. (2023). Risk Response In Construction Project: A Review Study. Journal Of Engineering, 29(08 Se-Articles), 121–137. Https://Doi.Org/10.31026/J.Eng.2023.08.09
Handoko, J. R. (2015). Pengaturan Risiko Hujan Dalam Kontrak Serta Dampak Dan Kendalanya Padaproyek Konstruksi. Jurnal Dimensi Pratama Teknik Sipil, 4(2).
Jamal, J., & Ian, M. R. (2025). Analisis Faktor Penyebab Keterlambatan Proyek Konstruksi Di Indonesia. Jurnal Kajian Teknik Sipil, 10(1), 1–8.
Kemenpupr. (2024). Jdih.Pu.Go.Id. No. 12.
Mensekneg. (2023). Peraturan Presiden Republik Indonesia Nomor 39 Tahun 2023 Tentang Manajemen Risiko Pembangunan Nasional. Kementerian Sekretariat Negara Ri, 167426, 1–19.
Muntadhimah, I., Nuswantoro, W., & Lendra, L. (2025). Faktor-Faktor Penyebab Keterlambatan Penyelesaian Proyek Konstruksi Gedung Di Kota Palangka Raya. Portal: Jurnal Teknik Sipil, 17(1), 221–229.
Nabut, Y. V, Henong, S. B., & Pattiraja, A. H. (2021). Analisa Faktor-Faktor Yang Paling Dominan Penyebab Keterlambatan Proyek. Jurnal Teknik Sipil Cendekia (Jtsc), 2(2), 182–190.
Ph.D. Ummul Aiman, S. P. D. K. A. S. H. M. A. Ciq. M. J. M. P., Suryadin Hasda, M. P. Z. F., M.Kes. Masita, M. P. I. N. T. S. K., & M.Pd. Meilida Eka Sari, M. P. M. K. N. A. (2022). Metodologi Penelitian Kuantitatif. In Yayasan Penerbit Muhammad Zaini.
Putri, D. F., Widiastuti, E., Afrila, H., & Hidayat, G. (2025). Scheduling Analysis Of Plan , Realisation , And Estimation By Using Precedence Diagram Method ( Pdm ) ( Case Study : Construction Development Project Multi-Purpose Sports Hall Phase Iv In Katingan Regency ). 9(1), 1–9.
Rizal, A. H., Fay, S., & Krisnayanti, D. S. (2024). Pengaruh Biaya Terhadap Penyebab Keterlambatan Penyelesaian Proyek Konstruksi Bendungan. Jurnal Teknik Sipil, 13(1), 55–66.
Santoso, R. (2023). Analisis Persepsi Cuaca Hujan Terhadap Proyek Konstruksi, Pada Proyek Apartemen Solterra. Jurnal Tera, 3(2), 33–45.
Siberut, P., Mentawai, K., & Barat, S. (2025). Analisa Manajemen Risiko Proyek Di Daerah 3t ( Terluar – Terdepan – Tertinggal ). Studi Kasus Pembangunan Jalan. 24(01).
Stefani Switly Peginusa. (2025). Analisis Dan Strategi Mitigasi Risiko Dalam Implementasi Proyek Konstruksi Hijau. Journal Konstruksi Dan Infrastruktur Teknik Sipil dan Perencanaan, 13(1), 29–36.
Sundari, S. (2014). Faktor-Faktor Yang Mempengaruhi Keterlambatan Proyek Konstruksi Di Maluku Tengah. 1–146. https://repository.its.ac.id/id/eprint/70615
Tinambunan, Y. (2024). Jurnal akuntasi mengenai risiko. 3(01), 10–19.
Vega, P. N., & Castresana, U. L. (2025). Sustainability in project risk management methodologies through the AHP-TOPSIS method applied to logistics and supply chain management. Environmental and Sustainability Indicators, 26, 100719. https://doi.org/https://doi.org/10.1016/j.indic.2025.100719
Wang, L., Cui, S., Li, Y., Huang, H., Manandhar, B., Nitivattananon, V., Fang, X., & Huang, W. (2022). A review of the flood management: from flood control to flood resilience. Heliyon, 8(11), e11763. https://doi.org/10.1016/j.heliyon.2022.e11763
Wirahadikusumah, R. D., Sapitri, Susanti, B., & Soemardi, B. W. (2018). Risk in government’s estimate for toll road: Based on investors’ perspective. International Journal on Advanced Science, Engineering and Information Technology, 8(2), 475–482. https://doi.org/10.18517/ijaseit.8.2.4322
Yuliana, C., & Hidayat, G. (2017). Manajemen Risiko pada Proyek Gedung Bertingkat di Banjarmasin Risk Management in Multi-storey Building Project in Banjarmasin). Info Teknik, 18(2), 255–270.
Zaidan, A. R., Soeryodarundio, K., & Setiono, S. (2024). Analisis Manajemen Risiko Proyek dengan Metode Severity Index ( SI ) pada Proyek Pembangunan Gedung X Kota Surakarta. Globe: Publikasi Ilmu Teknik, Teknologi Kebumian, Ilmu Perkapalan, 2(3), 211–221.
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Jurnal Infrastruktur

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.